Blog
Sep 10, 2024

Full Home Remodeling Timeline

Embarking on a full home remodeling project is an exciting yet complex undertaking that typically spans 26 to 52 weeks (6 months to a year). This comprehensive process transforms your living space, enhancing both functionality and aesthetics. From initial concept discussions to the final touches, each stage requires careful planning and execution.

full home remodeling timeline

If you are looking for a good Denver Home Remodeler, browse Colorado Builders Group’s services, we are the top choice of Denver Residents for Everything Remodeling.

Here’s how long it takes to complete each step involved in the full home remodeling process:

  1. Discuss Your Home Remodeling Ideas (1–2 weeks)
  2. Assess The Structural Integrity Of Your Home (1–2 weeks)
  3. Prepare Designs, Floor Plans, and 3D Renderings (3–6 weeks)
  4. Acquire Full Home Remodel Permits from Authorities (2–6 weeks)
  5. Tackle Moisture & Water-Related Concerns (1–2 weeks)
  6. Demolish Any Structures, if required (1–2 weeks)
  7. Install Framing for New Walls (2–4 weeks)
  8. Install Lighting, Plumbing, Electrical & Mechanical Rough-in Elements (3–5 weeks)
  9. Install Insulation, Ceiling, & Drywall (3–5 weeks)
  10. Prime & Paint Walls And Other Surfaces (2–4 weeks)
  11. Install Roofing, Siding, Flooring, Windows, And Doors (3–6 weeks)
  12. Install Baseboards, Crown Moldings, And Other Trim Elements (1–2 weeks)
  13. Connect Fixtures in Bathroom, Kitchen, & Other Rooms (1–2 weeks)
  14. Finalize The Exterior And The Basement Of Your Home (1–2 weeks)
  15. Final Touches, Cleanup, and Inspection (1–2 weeks)

Full Home Remodeling Process

1. Discuss Your Home Remodeling Ideas (1–2 weeks)

The first step in your remodeling journey involves brainstorming and discussing your vision with professionals. During this phase, you’ll share your ideas, preferences, and goals for the renovation. This collaborative process helps shape the project’s direction and ensures that your dreams align with practical considerations.

2. Assess The Structural Integrity Of Your Home (1–2 weeks)

A thorough evaluation of your home’s structure is crucial before any major changes. Professionals will inspect the foundation, load-bearing walls, and overall condition of the house. This assessment identifies potential issues that could impact the remodeling plans and helps in developing a safe and feasible renovation strategy.

3. Prepare Designs, Floor Plans, and 3D Renderings (3–6 weeks)

With ideas and structural assessments in hand, designers create detailed plans for your remodel. This stage includes drafting floor plans, selecting materials, and developing 3D renderings. These visual aids help you envision the final result and make informed decisions about layout, finishes, and overall design aesthetics.

4. Acquire Full Home Remodel Permits from Authorities (2–6 weeks)

Obtaining necessary permits is a critical step that ensures your remodel complies with local building codes and regulations. This process can vary in duration depending on your location and the scope of work. It may involve submitting plans, paying fees, and potentially making revisions based on feedback from local authorities.

5. Tackle Moisture & Water-Related Concerns (1–2 weeks)

Addressing any existing or potential moisture issues is essential for the longevity of your remodel. This phase involves identifying and resolving water-related problems such as leaks, poor drainage, or inadequate waterproofing. It’s worth noting that this stage can extend beyond the estimated timeframe if major issues are discovered, requiring more extensive remediation.

6. Demolish Any Structures, if required (1–2 weeks)

If your remodel involves removing existing structures or walls, this demolition phase prepares the space for new construction. It includes careful removal of designated elements, ensuring the structural integrity of remaining components, and proper disposal of debris.

7. Install Framing for New Walls (2–4 weeks)

With the space cleared, framing begins for any new walls or structural changes. This stage sets the physical boundaries of your new layout, creating the skeleton of your remodeled home. Precision is key, as this framing will impact all subsequent stages of the renovation.

8. Install Lighting, Plumbing, Electrical & Mechanical Rough-in Elements (3–5 weeks)

The rough-in phase involves installing the hidden but crucial components of your home. This includes running electrical wires, plumbing pipes, HVAC ducts, and setting up lighting fixtures. These systems are put in place before walls are closed up, ensuring everything is properly positioned for the finished space.

9. Install Insulation, Ceiling, & Drywall (3–5 weeks)

Once the rough-in work is complete, insulation is added to improve energy efficiency. Ceilings are then installed, followed by drywall to enclose the walls. This stage transforms the framed structure into recognizable rooms, providing a canvas for the finishing touches to come.

10. Prime & Paint Walls And Other Surfaces (2–4 weeks)

With walls in place, painting begins. This includes priming surfaces, selecting colors, and applying paint or other finishes. The duration can vary based on the complexity of the color scheme and any special techniques or finishes desired.

11. Install Roofing, Siding, Flooring, Windows, And Doors (3–6 weeks)

This phase focuses on both exterior and interior elements. Roofing and siding protect your home from the elements, while new windows and doors enhance both appearance and energy efficiency. Inside, flooring installation brings warmth and character to each room.

12. Install Baseboards, Crown Moldings, And Other Trim Elements (1–2 weeks)

Adding trim work brings refinement to your newly remodeled spaces. This includes installing baseboards, crown moldings, and other decorative elements that enhance the overall aesthetic and provide a polished look to walls and transitions.

13. Connect Fixtures in Bathroom, Kitchen, & Other Rooms (1–2 weeks)

The installation of fixtures brings functionality to your remodeled spaces. This includes setting up sinks, toilets, showers, kitchen appliances, and lighting fixtures. Each element is carefully positioned and connected, bringing your design vision to life.

14. Finalize The Exterior And The Basement Of Your Home (1–2 weeks)

Attention turns to completing any remaining exterior work and finalizing basement renovations if included in the project. This might involve landscaping, exterior painting, or finishing touches on lower-level living spaces.

15. Final Touches, Cleanup, and Inspection (1–2 weeks)

The last stage involves putting the finishing touches on your newly remodeled home. This includes a thorough cleanup, final adjustments, and a comprehensive inspection to ensure everything meets quality standards and building codes.

This timeline provides a general framework for a full home remodel, but it’s important to remember that each project is unique. Factors such as the scope of work, unexpected challenges, and even weather conditions can affect the duration. For a more accurate timeline tailored to your specific project, it’s advisable to consult with experienced professionals like Colorado Builders Group.

Browse Other Denver Remodeling & Construction Timeline Guides

 

Related Posts

See all related posts: ,